What happens next?
Your job can only be progressed when you accept the terms of your quotation and make the necessary payment as detailed in your quotation letter. Prompt Acceptance of Terms is strongly recommended to ensure timely completion of work on your site.
Once you accept the quotation NIE may have to obtain some or all of the following to meet your requirements:
- Approval from other landowners for the new or altered infrastructure including formal agreement to wayleaves or easements
- Planning permission from the DRD Planning Service. This planning permission is entirely separate from the planning approval you have been granted for your development. Full planning permission is required if NIE need to construct an overhead line over 100 metres in length
- Permission from DRD Roads Service to carry out work on public roadways
Please note that in some instances, because of the processes described above, it may take 9 months before the work can be completed. NIE strongly advises you to make an early application for your new supply or alteration to avoid any undue delays.